29th April 2019 Sancta Maria Louisburgh

  • Phase 3 Complete and handed over in Nov 2018
  • Phase 4 Existing building now completed and handed over 29.04.19
  • Additional 9 Classrooms fully refurbished including library, Science room, & internal court yard
  • Milestone reached whereby All existing Temporary mobile classrooms have now been removed from site

School have now taken possession of all classrooms, offices and ancillary rooms and are extremely pleased with their new facilities which are now being used to full capacity.

Phase 5 works are under way which include new 3G all weather pitch, basketball courts, carparking and bus layby with planned completion as June 2019.